It has been a while since we’ve heard from First Light! First Light is the 459-unit condo by West Bank going up at 3rd and Virginia. They just sent out an email update on construction:

The Level 1 slab has been completed bringing the structure to grade. We are now moving to the above grade structure. We anticipate completing the office levels early in the New Year and starting construction on the first residential level by Februrary. We have started mechanical and electrical work in the garage below grade. Site utility work will begin in the upcoming month.

Last we heard First Light was about 65% pending and will likely complete mid-2023. Initially scheduled to break ground in October 2019, they broke ground in mid-2020.

I own and manage Urban Living, a boutique Seattle and Bellevue real estate brokerage. I love lofts, floating homes, new construction, and mid-century moderns, but I will help you buy or sell just about anything!

Get in touch to:

  • Understand the market
  • Find your perfect home
  • Sell your home

Contact:

206-203-6242